Rydens Secondary School : Walton-on-Thames
cfp were commissioned as Architects and Cdm Coordinator to look at the re-planning and extension of this thriving secondary school.
The £1.8 million design provides eight new maths and three new DT classrooms, with associated communal facilities and links to the existing school. The contract was successfully run to a very tight budget and timescale. The overall programme was 9 months, but the Maths classrooms were handed over after 6 months.